A complete side entrance cut through the foundation with exterior stairs runs $18,000 to $28,000 in the GTA, and a walk-up stairwell excavated in the yard runs $22,000 to $45,000, according to CNB Renovation. Where the rear grade already slopes away, a walkout at grade is cheaper at $12,000 to $22,000.

Illustration: a concrete stairwell excavated in a side yard, with poured concrete retaining walls on both sides, steps descending to a doorway cut through the foundation wall, and a drain grate set into the landing at the bottom.
Illustration generated for this guide. Not a photograph of a real job, and not evidence of a price. The photographs further down this page were published by the companies named beside them.

Prices

What does a basement walkout or separate entrance cost?

This range rests on 4 independent named sources, across 11 priced lines. Every figure was re-read in August 2026 in the source that publishes it, and any figure whose source could no longer be read was removed rather than carried forward. Where two sources disagree, both rows are shown as their own sources published them; nothing is averaged and no range is widened to cover a gap.

Every figure below was read off the page named in its own row, in August 2026. Canadian dollars, before Ontario’s 13% HST unless a row says otherwise. The line under each item is the condition recorded with that figure: what the number covers, and what it does not.
ItemTypical rangeUnitSource
Side entrance, complete (36" door cut through the foundation wall with exterior stairs)Per project, for a door cut through the foundation wall with exterior stairs. The source says this is the most common form in semi-detached and detached homes.$18,000–$28,000per projectCNB Renovation (Toronto & GTA)
Walk-up stairwell entrance, complete (concrete stairwell excavated in the front or side yard, door at the bottom)Per project. The source attributes the higher price to excavation volume, and says the walk-up is common in older Toronto housing stock.$22,000–$45,000per projectCNB Renovation (Toronto & GTA)
Walkout basement, complete (rear yard grade already slopes away, door at grade with no stairs)Per project, and it assumes the rear yard grade already slopes away. The source notes excavation is still needed where the grade is level.$12,000–$22,000per projectCNB Renovation (Toronto & GTA)
Separate basement entrance in Toronto, all in (second opinion on the same scope)Per project, this source's Toronto band. The same table gives Thornhill the same $15,000 to $35,000 and Richmond Hill $15,500 to $36,000, so it is a GTA-wide figure rather than a Toronto-specific one.$15,000–$35,000per projectMS Builders (Toronto & GTA)
Excavation for the walkout and backfillA line item inside one worked example project, not a standalone price. The source publishes it as part of a full breakdown. Covers excavation for the walkout and the backfill.$5,000–$5,000line itemRock Basements (Toronto)
Cutting the door opening in the existing foundation wallA line item inside one worked example project, not a standalone price. The source publishes it as part of a full breakdown. Covers cutting the door opening in the existing foundation.$1,000–$1,000line itemRock Basements (Toronto)
Exterior waterproofing of the new opening (membrane plus weeping tile, 8 linear ft)A line item inside one worked example project, not a standalone price. The source publishes it as part of a full breakdown. Exterior membrane plus weeping tile over 8 linear feet of the new opening.$4,200–$4,200line itemCNB Renovation (Toronto & GTA)
Drainage installation with materialsA line item inside one worked example project, not a standalone price. The source publishes it as part of a full breakdown. The source lists it as drainage installation with materials, without saying where in the job it sits.$2,000–$2,000line itemRock Basements (Toronto)
Exterior concrete stairs, 4 risers with a landingA line item inside one worked example project, not a standalone price. The source publishes it as part of a full breakdown. Concrete stairs, 4 risers with a landing.$6,500–$6,500line itemCNB Renovation (Toronto & GTA)
BCIN-stamped architectural drawings for the permit applicationPer project, for the drawings only. The same table lists the permit application itself separately at $1,200 to $2,800.$1,500–$3,000per projectCNB Renovation (Toronto & GTA)
City of Toronto building permit fee, underpinning (the permit class that covers adding a below grade entrance), effective Jan. 1, 2026Per linear metre, effective January 1, 2026. This is the underpinning permit class, which is the one that covers adding a below-grade entrance. City fee only.$12.37–$12.37per linear metreCity of Toronto, Residential Underpinning permit guide

Prices

Where do the published prices disagree?

Each bar below is one published range, drawn to scale against the others quoted in the same unit. Nothing here is averaged: where two companies price basement walkout differently for what reads like the same job, both bars are drawn at the lengths their own sources published, and the gap between them is the thing worth looking at before you accept either bid.

Quoted per project5 published ranges, drawn against the widest figure in this group.
  • Side entrance, complete (36" door cut through the foundation wall with exterior stairs)$18,000–$28,000

    CNB Renovation (Toronto & GTA)

  • Walk-up stairwell entrance, complete (concrete stairwell excavated in the front or side yard, door at the bottom)$22,000–$45,000

    CNB Renovation (Toronto & GTA)

  • Walkout basement, complete (rear yard grade already slopes away, door at grade with no stairs)$12,000–$22,000

    CNB Renovation (Toronto & GTA)

  • Separate basement entrance in Toronto, all in (second opinion on the same scope)$15,000–$35,000

    MS Builders (Toronto & GTA)

  • BCIN-stamped architectural drawings for the permit application$1,500–$3,000

    CNB Renovation (Toronto & GTA)

Longest bar ends at $45,000, the widest figure any source in this group published per project.

Quoted line item5 published ranges, drawn against the widest figure in this group.
  • Excavation for the walkout and backfill$5,000

    Rock Basements (Toronto), one published figure rather than a range

  • Cutting the door opening in the existing foundation wall$1,000

    Rock Basements (Toronto), one published figure rather than a range

  • Exterior waterproofing of the new opening (membrane plus weeping tile, 8 linear ft)$4,200

    CNB Renovation (Toronto & GTA), one published figure rather than a range

  • Drainage installation with materials$2,000

    Rock Basements (Toronto), one published figure rather than a range

  • Exterior concrete stairs, 4 risers with a landing$6,500

    CNB Renovation (Toronto & GTA), one published figure rather than a range

Longest bar ends at $6,500, the widest figure any source in this group published line item.

10 of the 11 rows in the table are drawn here. 1 is the only row quoted in its unit, and one bar on its own is not a comparison. Every one of them is in the table above with its own source.

Method

What is the difference, physically?

A separate entrance is five priced jobs stacked on one another, and the table above prices them separately because a quote can leave any of them out. What the drawing shows is that the hole in the wall is the small part: the stairwell, the retaining walls and the drain at the bottom are the rest of the money.

A stairwell cut into the yard, a door cut into the wall
1
Excavation for the stairwell in the front or side yard
2
Concrete stairs and the retaining wall holding the soil back
3
The door opening cut through the existing foundation wall
4
Membrane waterproofing the new opening
5
Weeping tile and drainage at the bottom of the stairwell. See "weeping tile" below

Prices

What drives the price?

Access, depth and scope move basement walkout pricing more than anything else in Toronto. Each factor below is one reason two quotes for what sounds like the same job can be thousands of dollars apart.

  • Which of the three configurations your lot allows: a grade-level walkout at the rear is the cheapest, a side door with stairs is mid, and a fully excavated walk-up stairwell is the most expensive because of excavation volume (CNB Renovation)
  • Excavation and backfill volume, which Rock Basements lists as the single largest line item at $5,000, ahead of the block foundation wall at $6,000 for the stairwell itself
  • Whether an engineered lintel is needed over the opening: CNB lists $1,800 for the beam plus $600 to $1,200 for the structural engineer letter that the permit requires
  • Waterproofing the perimeter of the cut from outside, listed at $4,200 for 8 linear feet of membrane plus weeping tile by CNB and at $2,000 for wall waterproofing plus $2,000 for drainage by Rock Basements
  • Drainage at the base of the stairwell, which is what stops the new well from becoming a bathtub; Leaquida prices a window well drainage system alone at $300 to $1,200 per well
  • Site access: tight urban Toronto lots, narrow side yards and utilities that have to be relocated push the price toward the top of every published range (RenoDuck)
  • Whether the basement unit needs a code-compliant egress window as well as the entrance; the entrance does not replace the escape window requirement
  • Whether the entrance is done alone or bundled with basement finishing: CNB says combining them saves $4,000 to $8,000 because plumbing, electrical and framing rough-in happen in one mobilization
  • Finishing items that are easy to forget in a quote: code-required railings ($1,400), the pre-hung steel door and interior frame ($1,100) and the exterior concrete stairs themselves ($6,500) in CNB's itemized job

Record

What's specific to Ontario and Toronto?

Ontario adds 13% HST to every figure on this page, Toronto requires permits for most below-grade structural work, and both change what you actually pay. These are the local rules and subsidies that a national price guide leaves out.

  • HST: renovation contracts in Ontario are fully taxable, so add 13% HST on top of every quoted figure above. Contractor per-project prices in this guide are pre-tax.
  • A City of Toronto building permit applies. The City's own Residential Underpinning guide states the service is a 'Building Permit for underpinning of the foundation of an existing house' and that 'One may also underpin to reinforce an existing foundation or to add a below grade or partly below grade entrance to an existing house.'
  • Permit fee, from the City's own page: underpinning is charged at $12.37 per linear metre, effective Jan. 1, 2026. If the project also creates a secondary suite, the City's Secondary Suites guide lists interior alterations for Group C at $11.53 per square metre plus a Residential Unit Fee of $56.33 per unit, both effective Jan. 1, 2026. Contractor pages quoting a flat permit price are quoting their own bundled service, not the City's rate.
  • Engineer involvement is not optional in practice. The City's underpinning page states: 'In all circumstances of underpinning, whether the underpinning was required to be designed by a Professional Engineer or not, you will be required (at the minimum) to provide testing and reports by a Professional Engineer during the first and last stages of the construction in order to pass inspections.'
  • The City also states that professional design and field review is required where the foundations are to be constructed below the level of the footings of an adjacent building and within the angle of repose of the soil, or the underpinning exceeds 1200 mm of laterally unsupported height, or the soil is clay or silt. Much of Toronto sits on clay, so budget for it.
  • If the basement becomes a second dwelling unit, the City's Secondary Suites guide confirms a building permit is required for the interior alteration to add a second dwelling unit smaller in area than the primary unit in an existing detached house, semi-detached house or townhouse, and names a basement apartment as the common example.
  • Escape window rule for a basement second unit, from Ontario's own second-unit guidance: a ground floor or basement escape window needs a minimum area of unobstructed opening of not less than 0.38 sq. m (4.1 sq. ft.), 460 mm (18 inches) or more for the openable portion of the window, and a maximum of 900 mm (2 ft 11 in) above the floor or steps. Adding a separate entrance does not remove this requirement.
  • Contractor-quoted permit and drawing packages are separate money from the City fee. CNB publishes $1,200 to $2,800 for handling the building permit application, $1,500 to $3,000 for BCIN-stamped architectural drawings and $600 to $1,200 for a structural engineer letter, and lists zoning confirmation at the zoning desk as $0.
  • Timeline is a cost in itself for a rental plan. CNB publishes 3 to 6 weeks for Toronto Building Division permit processing, 5 to 8 business days of active construction and 6 to 10 weeks total; Rock Basements says drawings and permits can be done within a month and the work takes 2 to 4 weeks depending on weather.

Prices

How can I pay less?

Bundling work into one excavation, reusing what is already there, and getting the sequence right are what actually cut a basement walkout bill in the GTA. Each lever below is tied to a figure in the table above.

  • Check your grade before you budget. If the rear yard already falls away from the house, CNB's walkout scope is $12,000 to $22,000 against $22,000 to $45,000 for a stairwell that has to be excavated. The same door in a different spot on the same lot can differ by $20,000.
  • Bundle the entrance with the basement finishing. CNB publishes savings of $4,000 to $8,000 when both are quoted together, because plumbing, electrical and framing rough-in happen in one mobilization.
  • Get an itemized quote, not a lump sum. Rock Basements and CNB both publish line-by-line breakdowns, so you can ask any other bidder to price the same items and see who quietly dropped the waterproofing or the drain.
  • Do not let anyone cut the wall without exterior waterproofing on the opening. CNB names this as the number one failure mode they see on competitor jobs, and $4,200 of membrane and weeping tile is far cheaper than reopening a finished stairwell.
  • If you need more than one window well, book them in one visit. Egress Windows Toronto charges $800 to $1,500 for the first well and offers a discounted rate on each additional unit done at the same appointment because the crew and equipment are already on site.
  • Separate the City fee from the contractor's permit service in your comparison. The City's underpinning rate is $12.37 per linear metre; the $1,200 to $2,800 you see on contractor pages is their fee for preparing and running the application.
  • Price the egress window at the same time as the entrance, not after. The entrance does not satisfy the escape window rule for a basement bedroom, and discovering it late means excavating twice.
  • Compare window well quotes on the drainage, not the shell. Leaquida prices the well material at $400 to $2,800 but the drainage system at $300 to $1,200 separately, so a cheap quote is often a well with no gravel base and no tie-in to the weeping tile.

Method

How did we research these numbers?

Every price on this page was re-read in the page that publishes it, and the sentence carrying it was recorded so the figure can be checked rather than trusted. Where two Canadian sources disagree, WaterproofingIndex shows both rather than averaging them into a number neither company quoted.

  • GTA contractors price this job by how much earth has to move, not by the door. CNB Renovation publishes $12,000 to $22,000 for a walkout where the rear grade already falls away, $18,000 to $28,000 for a side door cut through the foundation with exterior stairs, and $22,000 to $45,000 for a walk-up stairwell dug into a front or side yard, because of the excavation volume. Their headline range for the whole category is $18,000 to $45,000.
  • MS Builders lands in the same band on the all-in number: $15,000 to $35,000 for Toronto, and $13,000 to $38,000 across North York, Etobicoke, Markham, Thornhill, Richmond Hill, Mississauga and Vaughan.
  • Where a low and a high are published but no single figure, the 'typical' column here is the midpoint of that same source's own published range. It is arithmetic on one source, not a blend of several. Where a source published a real point figure it is used directly: the $21,600 typical for a side entrance is CNB's own itemized total for a 2025 semi-detached job in Etobicoke.
  • Rock Basements publishes a full line-item breakdown for a standard walkout: excavation and backfill $5,000, footings $1,500, door cutout in the existing foundation $1,000, drainage installation with materials $2,000, waterproofing walls $2,000, concrete slab $1,000, block foundation wall $6,000, forming and pouring stairs $2,200, top layer foundation concrete $1,800. Their calculator headline is $25,000 with permits, structural tie and waterproofing, and they add that drawings and permits cost a few thousand more.
  • Sources disagree sharply at the low end, and the disagreement looks like scope, not market. RenoDuck publishes $2,500 to $10,000 for an Ontario separate entrance with $6,250 average, and Level Up Group publishes $2,500 to $10,000 as well, but both are describing bulkhead and simple door scopes. RenoDuck's own dedicated walkout page publishes $10,000 to $30,000 for the GTA. None of the sub-$10,000 numbers were used as rows here because they do not cover a permitted, engineered, waterproofed foundation cut.
  • One page was rejected for internal contradiction: Renomod's separate-entrance guide prices a standard side entrance at $18,000 to $28,000 in one section and $10,000 to $20,000 in another, and a premium walk-out at $35,000 to $65,000 in one section and $15,000 to $30,000 in another. No figure from it was used.
  • Window well pricing spreads by scope. Leaquida publishes $1,000 to $5,000 per well for a full replacement, and Egress Windows Toronto publishes an $800 to $1,500 installation fee for the first well with a discount on additional wells done in the same visit.
  • Every price above is a contractor's published figure and excludes HST. The only government figure in the table is the City of Toronto's own permit fee rate.

Sources

Companies

Who can do the work?

WaterproofingIndex tracks 14 basement walkout contractors across the Greater Toronto Area, rated 4.77★ on average. The three below rank highest on our review-weighted score, based on WaterproofingIndex's analysis of 14 GTA businesses, August 2026.

  • SB Excavation2

    SB Excavation

    73/100 WaterproofingIndex Score

    1.4 km from Mimico centre

    MimicoBasement Waterproofing
    • Says it is insured
    • Says it carries WSIB coverage

    Its own website describes below-grade water work

  • JKRC Group Ltd3

    JKRC Group Ltd

    69/100 WaterproofingIndex Score

    0.9 km from Islington-City Centre West centre

    Islington-City Centre WestFoundation Repair
    • Says it is licensed
    • Says it is insured

    Its own website describes below-grade water work

See all 14 basement walkout contractors on WaterproofingIndex

Photographs

What do the photographs on these listings show?

Every picture below was published by the company under it, on its own business listing, and WaterproofingIndex did not take any of them. Each of these companies describes below-grade water work on its own website, which is the same relevance check every profile on this site publishes. They are still not all the same kind of picture: some show a floor opened up mid-job, some show a truck or an office with the company's sign on it. None has been checked against a job in your area, and none is evidence of a price. They are here because a company that publishes its own excavation is showing you something a quote cannot.

Prices

Can I work out my own number?

The table above is the market. These calculators put your own basement into it, and they add the HST and any City of Toronto subsidy that applies.

Record

What do the terms on a below-grade quote mean?

These are the words that appear on a basement walkout quote without being explained. Each one changes what you are buying.

egress window
A basement window large enough to escape through, required by the Ontario Building Code for a bedroom in a basement unit. A separate entrance does not satisfy the requirement.
underpinning
Deepening an existing foundation by excavating and pouring new footings in sequenced sections beneath the old ones. It is how a basement gains height without moving the house, and it is structural work that needs engineered drawings and a permit.
weeping tile
The perforated drain pipe laid in stone alongside a foundation footing. It has nothing to do with tile: the name is from the clay pipe sections originally used. It collects groundwater before it reaches the wall and carries it to a storm connection or a sump pit.
sump pit
A lined basin cut into the basement floor at the low point of the drainage system. Water collected by the weeping tile runs into it and a sump pump ejects it away from the house.
bench footing
The cheaper alternative to underpinning: the floor is lowered but a concrete bench is left running along the base of the existing wall so the footing is never undermined. It costs less and takes floor width instead.

Prices

Which cost guide should I read next?

Below-grade jobs overlap, and the wrong guide gives you the wrong budget. These three are the ones most often quoted alongside basement walkout.

Frequently asked questions

How much does a basement walkout cost in Toronto?

It depends on which of three configurations your lot allows. CNB Renovation publishes $12,000 to $22,000 for a true walkout where the rear grade already slopes away, $18,000 to $28,000 for a side door cut through the foundation with exterior stairs, and $22,000 to $45,000 for a walk-up stairwell excavated in the front or side yard. MS Builders publishes $15,000 to $35,000 for Toronto overall. All figures are before HST.

What does a separate side entrance actually break down into?

CNB Renovation published a real 2025 Etobicoke job on a 1948 semi-detached with a poured concrete foundation: core drill and door frame rough-in $3,400, exterior waterproofing with membrane and weeping tile over 8 linear feet $4,200, engineered structural lintel $1,800, concrete exterior stairs with 4 risers and a landing $6,500, code-required wrought iron railings $1,400, interior door frame and pre-hung steel door $1,100, permit and BCIN drawings $3,200. Total $21,600.

Do I need a permit to cut a door into my foundation in Toronto?

Yes. The City of Toronto's Residential Underpinning guide describes the service as a building permit for underpinning the foundation of an existing house, and states that you may underpin to reinforce an existing foundation or to add a below grade or partly below grade entrance to an existing house. If the basement is also becoming a second dwelling unit, the City's Secondary Suites guide confirms a separate building permit is required for that interior alteration, naming a basement apartment as the common example.

What does the City of Toronto charge for the permit?

The City's own underpinning page lists a fee of $12.37 per linear metre effective Jan. 1, 2026. If the project also creates a secondary suite, the City's Secondary Suites page lists interior alterations for Group C at $11.53 per square metre plus a Residential Unit Fee of $56.33 per unit, also effective Jan. 1, 2026. That is the City's charge only. Contractors quote their own fee on top for preparing and running the application, typically $1,200 to $2,800 per CNB.

Do I need an engineer, and what does that add?

In practice yes. The City of Toronto states that in all circumstances of underpinning, whether or not the design had to be done by a Professional Engineer, you must provide testing and reports by a Professional Engineer during the first and last stages of construction in order to pass inspections. Full professional design and field review is required where the work goes below an adjacent building's footings within the angle of repose, exceeds 1200 mm of laterally unsupported height, or the soil is clay or silt. CNB publishes $600 to $1,200 for a structural engineer letter and $1,500 to $3,000 for BCIN-stamped drawings.

What does a window well cost on its own?

Leaquida publishes $1,000 to $5,000 per well for a full replacement, itemized as $400 to $2,800 for the well material, $400 to $1,500 for labour and installation, $300 to $1,200 for the drainage system and $50 to $300 to remove the old well. Egress Windows Toronto charges $800 to $1,500 for the first well and discounts additional wells done in the same visit. Artech Landscaping publishes $1,000 to $2,000 for a basic 3 ft by 4 ft fiberglass or plastic well and $1,500 to $3,000 for a standard 4 ft by 8 ft one.

How do I stop the new stairwell from flooding?

Drainage at the base of the stairwell and waterproofing on the perimeter of the cut are the two line items to insist on. Rock Basements prices drainage installation with materials at $2,000 and wall waterproofing at $2,000 within a standard walkout. CNB names an unwaterproofed cut as the top failure mode they see on competitor jobs and says it creates a guaranteed leak point within two to three winters, so they waterproof the full opening perimeter from outside on every job.

Questions to ask your contractor

  • Who pulls the building permit, and is the engineered drawing inside your price?
  • How is the opening supported once the wall is cut?
  • How is the stairwell drained, and where does that water go? Sourced project pricing
  • Is the new opening waterproofed and flashed, and with what?
  • Have you checked zoning and the lot lines for this, or is that on us?